Report construction and building work

It is the client’s responsibility to report construction and building work to the Danish Working Environment Authority. Work must be reported before it is commenced.

As the client you must report construction and building work to the Authority if the work is of a certain scope.

This is the case if you expect that one of the following two conditions will be met:

  • The work will go on for more than thirty days and there will be at least twenty employees working at the same time.
  • The expected workload will exceed 500 man days.

The report must be made before work is commenced.